How Long Does It Take to Build an ADU?

Advertised ADU timelines usually start the clock at permit issuance and stop it at set day. Measured honestly — from your first phone call to a tenant with keys — a detached ADU takes nine to fourteen months. Conversions run shorter. Here is the full breakdown.

Updated Aug 2026 6 min read
9–14 mo
Detached, door to door
6–9 mo
Garage conversion
2–4 mo
Permitting alone

Phase by phase

Typical detached ADU schedule
PhaseDurationWhat happens
Feasibility1 – 2 weeksZoning, utilities, access and budget confirmed
Financing4 – 8 weeksRuns parallel with design
Design & engineering4 – 8 weeksPlans, structural, Title 24
Permitting8 – 16 weeksPlan check, corrections, issuance
Site work & foundation3 – 5 weeksTrenching, utilities, slab or piers
Construction or set8 – 20 weeksFactory set or full site framing to finish
Inspections & CO2 – 4 weeksFinal sign-offs and certificate of occupancy

The five delays that actually happen

Notice that four of the five are front-loaded and preventable. Utility scheduling is the one true external dependency, which is why we file service applications the week the permit is submitted rather than the week it issues.

  • Incomplete first submittal — one resubmittal cycle costs 4 to 8 weeks
  • Utility company scheduling for a new service or meter set, frequently 6 to 12 weeks
  • Owner-driven design changes after plans are in plan check
  • Sewer or septic capacity discovered late, forcing redesign
  • Financing approval lagging behind permit issuance and stalling the start

How to compress the schedule

Run design, financing and utility applications in parallel instead of sequentially — that alone saves six to ten weeks. Use a plan that has already been permitted in your jurisdiction, or a pre-approved plan where the city offers one. Choose modular if your lot has crane access, since factory production overlaps site work. And lock your finish selections before framing; late selections stall trades in the most expensive part of the schedule.

Frequently asked questions

Find out what your lot can build

A free feasibility check confirms what's allowed at your address, what it costs and what it would rent for — before you spend a dollar on design.